What the fee covers
A retrospective application is drawn from what exists, so the survey does the heavy lifting. From £845 inc survey we measure the work as built, draw the plans and elevations to match it, prepare the forms with the work shown as already built and write a short statement explaining why the work is acceptable.
Where the house differs from the approved plans, we show the difference clearly, so the officer sees what changed. Typical cases are an extension built larger than approved, or a loft built but never applied for.
Is it lawful to apply after building?
Yes. The Town and Country Planning Act says planning permission may be granted for development already carried out, or carried out without complying with a condition. It is an everyday route, not a last resort.
What matters is how you present it. National policy says that evidence that unauthorised development was intentional should be given substantial weight, so an application that explains what happened and why the result is acceptable is stronger than one that hopes the officer will not look.

How long before the council can act
Time limits for enforcement are set by law. For building operations the council now has ten years, a period lengthened by a change that came into force on 25 April 2024. That is a long time, which is why a buyer's solicitor may ask about old work.
The council may also decline to determine an application that covers matters in an enforcement notice already issued. If you have received a notice, tell us first, because the order of events changes the advice.
What comes after a decision
A householder application is decided in eight weeks as a target. If it is refused, the appeal clock is 12 weeks. Our planning appeals service starts at £495.
Sometimes the council grants permission subject to changes, such as obscure glazing or a lower roof. We tell you early which changes are likely, because they are cheaper to plan for than to rebuild.

Start with a free check
Send the address, what was built and when. We check the history and the constraints and say what we would do. Read about our retrospective planning service for the sheets we produce.
The figures, with sources
s73A
Planning permission may be granted for development already carried out.
Source: Town and Country Planning Act 1990, section 73A, checked 17 Oct 2026
10 years
Time limit for enforcing against building operations, after the 2024 change.
Source: Town and Country Planning Act 1990, section 171B, checked 17 Oct 2026
s70C
Council may decline to determine an application about matters in an earlier enforcement notice.
Source: Town and Country Planning Act 1990, section 70C, checked 17 Oct 2026
DM8
Policy giving substantial weight to evidence that unauthorised development was intentional.
Source: National Planning Policy Framework, checked 15 Oct 2026
£548
Fee for a householder application to regularise work on a single dwelling.
Source: Ribble Valley Borough Council, national fee table from 1 April 2026, checked 17 Oct 2026
8 weeks
Statutory target for deciding a householder application.
Source: Development Management Procedure Order 2015, article 34, checked 15 Oct 2026
12 weeks
Period to appeal a householder refusal, from the decision notice.
Source: Development Management Procedure Order 2015, article 37, checked 15 Oct 2026
Questions
Will the council make me knock it down?
Only if it refuses the application and takes enforcement action, which is its choice. Applying promptly and showing why the work is acceptable is the usual first step.
Do I need building regulations as well?
Often, yes. Work already built may need a regularisation application; see our regularisation drawings service.
Can you survey work that is already finished?
Yes. The survey is how we record what is there, and it is included in the price.
What if I got permission but built something different?
That is a common case. We draw the as-built scheme against the approved plans and the application explains the difference.
The fee for retrospective planning application
Retrospective planning application
from £845
inc survey (£645 if you supply measured drawings). No VAT to add.
Get a fixed quote from £845What you get
- A measured survey recording what is built, included
- As-built plans and elevations
- The approved plans compared against what exists
- A short statement for the case officer